People within the Federal acquisition environment are rightly pleased to see the July 2026 reforms to the Cost Accounting Standards via publication of a final rule that became effective 07 August 2026. (See 91 FR 42139.) The reforms:

  • Eliminated CAS 408 (Compensated Personal Absence) in its entirety
  • Eliminated CAS 411 (Acquisition Costs of Material) in its entirety
  • Significantly reduced requirements of CAS 404 (Capitalization of Tangible Assets) and CAS 409 (Depreciation of Tangible Capital Assets). The Standards were eliminated but a few parts were moved to other existing Standards.

At this point, instead of 19 Standards, we have 15. Yay! Good for us all.

Except why did it take so long?

Let’s review the history of this rulemaking action. Congress first told the CAS Board to take action via Section 820 of the 2017 National Defense Authorization Act (NDAA). That was literally nine years ago. Two years later, the CAS Board published a Staff Discussion Paper (SDP) in March 2019, to establish a “a global roadmap to help guide [the Board’s] approach to conformance” of CAS and GAAP. That roadmap identified seven standards (404, 407, 408, 409, 411, 415, and 416) as most suitable for potential conformance to GAAP. Apparently, the Board is still working on Standards 415 and 416, as they were not part of the July 2026 final rule.

Eighteen months later (18 September 2020), the Board published another SDP “to solicit views with respect to the Board's initial assessment of CAS 404 and CAS 411….”

A formal Advanced Notice of Proposed Rulemaking (ANPRM) was issued 27 June 2024 to address Standards 408 and 409. Not quite four years after the SDP was issued and public comments received. The comments were sufficient to convince the Board that the two Standards were ripe for reform.

Another formal ANPRM was published 17 January 2025 to address the Board’s conclusions on Standards 404 and 411. Literally more than four years after the second SDP was published.

Four years. Let that sink in.

Yeah, yeah, yeah. Right. There was a slight COVID-19 interruption. There was a lack of an industry Board member. The CAS Board Chair was “acting” because there was no Senate-confirmed OFPP Administrator. All true. Valid points. But also just excuses because the business of the Federal government shouldn’t be paused for FOUR YEARS because some folks lost the keys to the file cabinet. Or so it seems to us here at Apogee Consulting, Inc.

The next step in the CAS rulemaking process, a formal Notice of Proposed Rulemaking (NPRM), was published 11 September 2025 to address all four Standards: 404, 408, 409 and 411. That was what? Less than two years after one ANPRM and less than one year after the other one. That was quick, given the historical bar established by the Board.

So now we have a Final Rule, published 08 July 2026. Less than a year after the NPRM. Super quick, right?

Only let’s not forget that the original SDP was published in 2020. We don’t think six years is a timeline in which to take pride.

The Department of War wants its forces to “move at the speed of relevance.” It has concluded that the old paradigms must give way to new ways of operating. From an article by Robbin Laird dated 31 March 2026 at www.defenseinfo.com.

Where armies and policymakers once relied on warning times and slow mobilization, they now confront adversaries, technologies, and social currents that move at the speed of relevance, upending the calculus of deterrence and defense planning.

Against this backdrop, the central strategic imperative is no longer to eliminate chaos or restore some lost order, but to build national systems, forces, and cultures that thrive amid it.

The security of the twenty-first century will belong to those who master the art of chaos management: sensing, adapting, and responding rapidly to events, even as crises multiply and old frameworks collapse.

Sense; adapt, respond. Do it quickly. Cool, cool, cool.

Only the CAS Board doesn’t seem to have gotten the message. They seem to be moving at the speed of bureaucracy rather than the speed of relevance.

Let’s be clear: reforming the CAS is a good thing. We applaud it. Only—why did it take so freaking long to accomplish?

One possible reform: the CAS Board has no timeline in which to take action. The Board can let the public input from SDPs and ANPRMs and NPRMs lie fallow for years because it can and because nothing forces the Board to move forward. Let’s reform the enabling statutes to require Board action within six months of public comment period closure. If you did that, we bet you’d see some real speed.

 

Newsflash

Effective January 1, 2019, Nick Sanders has been named as Editor of two reference books published by LexisNexis. The first book is Matthew Bender’s Accounting for Government Contracts: The Federal Acquisition Regulation. The second book is Matthew Bender’s Accounting for Government Contracts: The Cost Accounting Standards. Nick replaces Darrell Oyer, who has edited those books for many years.