• Increase font size
  • Default font size
  • Decrease font size
Apogee Consulting Inc

DCAA Tells Auditors How to Support Contracting Officer Negotiations

E-mail Print PDF

DCAA has published some significant audit guidance recently, much of which we have discussed on this website. We usually get access to new audit guidance (issued in the form of Memoranda for Regional Directors) a couple of weeks in advance of publication on the DCAA’s website. Recently, however, DCAA has experienced delays in putting its new audit guidance on the Internet; publication of some guidance has been delayed as much as six weeks. Typically, we wait to discuss new guidance until it’s available to the public, but now we’ve lost patience—and so we have some things to discuss with you.

First, you may remember that we’ve taken issue with the latest DCAA audit guidance that provides direction to auditors on how to evaluate contractors’ estimates of future indirect cost rates. For example, we had very few nice things to say about MRD 10-PSP-021(R) and many negative ones. Prior to that, we had even fewer things--and many more negative things—to say about MRD 10-PSP-018(R). Our overarching thought, based on the recent guidance, is that, in essence, DCAA as an organization has gone insane.

You can’t have worked in the arena of government contract cost accounting for the past two years and not noticed the intense barrage of criticism leveled at the audit agency—much of it politically driven, unwarranted, and based on flawed review methodology. One of the more frequent criticisms has been that DCAA has not met the independence standards imposed by generally accepted government auditing standards (GAGAS). That accusation hasn’t been true—or at least, it’s been rarely true—but it has driven the audit agency into a virtual obsession with maintaining independence. That obsession has impacted auditor interactions with contractors, DCMA contracting officers, and buying commands. As a result, issuance of audit reports has slowed to a crawl. And those reports that have been issued, generally have been riddled with factual errors and other quality shortcomings, because (a) auditors are afraid to openly communicate with those they are auditing (as well as those agency customers requesting the audits), and (b) once the auditors reach a preliminary finding, everybody (from the auditor to the supervisory auditor to the branch manager to the regional audit manager) is afraid to change it—even when confronted by facts that would lead a reasonable person to a different conclusion.

As we’ve noted many times on this website, it now takes roughly three times longer for DCAA to issue its audit reports, and those it does manage to issue don’t provide much value to anybody. We know DCMA is working hard to dissolve its dependence on the audit agency, and we recently noted some criticism from the DOD IG regarding DCMA’s efforts in that regard. Perhaps sensing that something must be done to turn the tide, DCAA issued MRD 10-PSP-023(R) on September 9, 2010.

Entitled, “Audit Alert on Auditor Attendance at Negotiations,” the audit guidance “encourages” DCAA auditors to support DCMA contracting officer negotiations—but also puts limits on that interaction. Following are a selected few quotes from the audit guidance—

  • It is DCAA’s policy to support contracting officers at negotiations where DCAA has issued an audit report on the contractor’s submission (e.g., price proposals, incurred cost submissions, termination claims), especially for complex submissions with significant audit issues. Attendance at pre-negotiation meetings with the contracting officer when requested to discuss audit report results is also encouraged.

  • Providing support and technical advice based on the auditor’s technical knowledge and expertise to help the contracting officer understand audit report results does not impair auditor independence. Answering questions about audit rationale/computations or giving advice regarding contractor rebuttals to reported results helps the contracting officer understand audit conclusions.

  • At times, contractors provide information and/or data directly to the contracting officer as a means to support their proposed positions in anticipation of or during negotiations. … The contracting officer may request DCAA assistance in understanding how that data impacts the reported audit conclusions. Auditors should support the contracting officer, to the extent possible, by providing advice on this data. This may include, for example, providing advice on the contractor’s rationale for a revised estimate, verifying data to the contractor’s books and records or other supporting data, or running various Government position scenarios using the data through audit report schedules and underlying spreadsheets, where appropriate.

The MRD includes a Frequently Asked Questions (FAQ) section. Here is a quote from that section of the MRD—

[The auditor] should answer the cost analyst’s questions to help him understand the audit conclusions and rationale. Providing such explanations is a normal part of any audit and does not impair your independence or otherwise violate GAGAS. … On occasion, it may also be appropriate to provide selected working papers which support complex audit computations to facilitate the contracting officer’s understanding.

The foregoing sounds good and would appear to be aimed at facilitating negotiations. However (as we noted above), the guidance also limits auditor interaction with the negotiating parties. In particular, the MRD discusses circumstances in which the auditor should seek to issue a “supplemental report” instead of supporting negotiations. The audit guidance says—

if the data is complex and/or represents a significant update to the audited proposal, and requires extensive review or analysis, the auditor would generally need to issue a supplemental report. … When a supplemental report is not issued, any documentation provided to the contracting officer of the work performed should be clearly marked to distinguish it from audit report results. For example, it should include a statement noting that the documentation contains advice provided in support of negotiations and does not represent audited data, nor a revised audit opinion. Nothing short of a supplemental report will result in a revised audit opinion.

We note that, once again, DCAA refuses to let new facts get in the way of its prior audit findings—leaving the contracting officer and buying commands stuck in limbo awaiting a supplemental report in order to have DCAA officially alter its original opinion based on receipt of new facts. The FAQ emphasizes this audit guidance, stating that, where the new facts require “extensive review or analysis,” then the auditor should—

recommend in writing that the contracting officer delay the negotiations for that part of the proposal to allow time for [a supplemental report to be issued]. … in the meantime, the contracting officer [should] proceed with the negotiations for the other parts of the proposal. [Emphasis added.]

The MRD also directs that auditors cannot review data provided by contractors during negotiations unless they have first performed sufficient audit work to support an opinion on that data. In such circumstances, the audit guidance directs auditors to “recommend to the contracting officer that the FAO audit the costs and issue a supplemental report.” That supplemental report, as you readers know, will take roughly 90 days to issue. Meanwhile, negotiations are stalled, the contract schedule becomes unattainable, and the resulting delay leads to increased costs. Not to mention, somebody somewhere doesn’t get what they need to accomplish their mission.

Undersecretary of Defense (A,T&L) Dr. Ashton Carter recently emphasized the importance of schedule in program execution. As this interview of Dr. Carter at DefenseNews.com reports—

Q. What's most important: requirements, cost, schedule?

A. The variable we pay the least attention to is time. And time is money. The default way of dealing with a program that is costing too much is to buy it more slowly. The default way of dealing with a program that is not meeting its requirements is to keep working on it until it does. So a five-year program stretches 10 years, and a 10-year program stretches to 15. That costs money. Those stretches don't cost more money per year, and no one feels a cost increase over 15 years. We need more programs with a philosophy of meeting a strict schedule.

Dr. Carter, if you want to see programs embrace a philosophy of meeting a strict schedule, you might want to start with evaluating why negotiations drag on so long and program delivery dates have already slipped before the first labor hour has been incurred. And should you do so, you might want to review the impact of DCAA’s recent audit guidance on that process.

We’re just saying.



 

Congress Adds Teeth to Foreign Corrupt Practices Act

E-mail Print PDF

The Foreign Corrupt Practices Act (FCPA) has two main provisions—(1) anti-bribery, and (2) books-and-records. The anti-bribery provision is enforced by the Department of Justice (DOJ), and the books-and-records provision is enforced by the Securities Exchange Commission (SEC). See our previous article on the topic here. As we told you, the FCPA originated from public revelations of corrupt payments made by Lockheed (now known as Lockheed Martin) in order to induce foreign governments to purchase its planes. So the inter-relationship between aerospace/defense companies and the FCPA goes back to the beginning.

Military services contractor Blackwater (now known as Xe Services LLC) was accused of committing bribery (but not violations of the FCPA) in April, 2010. Here’s a blog post that explores the allegations against the company. It states that several company executives—

--were charged with 15 counts of conspiracy to violate firearms laws, making false statements and representations on federally licensed firearms dealers' records, possession of machine guns, possession of other firearms (short-barrelled shotguns) not registered in the National Firearms and Registration and Transfer Record, and aiding and abetting

The blog post linked to a November, 2009 article by the New York Times alleging that senior Blackwater executives “authorized secret payments of about $1 million to Iraqi officials that were intended to silence their criticism and buy their support after a September 2007 episode in which Blackwater security guards fatally shot 17 Iraqi civilians in Baghdad, according to former company officials.”

The blog post summed-up the situation thusly—

Four former employees the Times interviewed for the November story claimed the payments were approved by the company's president and money was wired to Iraq from accounts in Jordan. The employees didn't know if the payments were actually made. The [Times] report said ‘Blackwater’s strategy of buying off the government officials, which would have been illegal under American law, created a deep rift inside the company, according to the former executives.’


A report by the Times Friday said, ‘While the indictment is somewhat limited in scope, it could be the government’s opening salvo in a broader offensive to bring criminal charges against the company. They could include charges for bribery and export violations, according to officials familiar with the case, perhaps under a strategy of turning former and current executives of the company against one another.’

From Lockheed to Blackwater, defense contractors have been caught up in the apparent need to offer illegal inducements to foreign officials, in order to secure favorable treatment. But a recent law aims to add teeth to the U.S. enforcement mechanisms.

This GovExec.com story by Robert Brodsky reported that the U.S. House of Representatives had passed the 2010 Overseas Contractor Reform Act (H.R. 5366). Mr. Brodsky’s story reported that the law (if passed and signed) “would require agencies to debar companies and individuals found in violation of the 1977 Foreign Corrupt Practices Act, and sever their existing government contracts and grants.”

The proposed bill contains a provision for an agency head to waive the penalty. In addition—as Mr. Brodsky notes—many contractors have been able to craft artful settlement agreements with the DOJ “that allowed them to admit wrongdoing, but not necessarily confess to bribery.” Thus, companies such as Halliburton and BAE Systems, that have paid millions of dollars in FCPA settlement agreements, might escape the bill’s intent.

This article at Corporate Compliance Insights noted some other issues—

Because most FCPA enforcement actions are settled through a non-prosecution agreement (NPA) or deferred prosecution agreements (DPA) … the bill may need some tweaking if it is to be effective.

Among other issues will be: is a company that agrees to an NPA or DPA to resolve an FCPA case ‘found to be in violation of the FCPA.’ Likely not.

Also, the bill defines ‘final judgment’ as when ‘all appeals of the judgment have been finally determined, or all time for filing such appeals has expired.’ Again, this assumes that all FCPA enforcement actions are resolved through actual judicial proceedings – which is not how FCPA enforcement works in many cases.

Other potential shortcomings with the bill is that it only applies to violations of the FCPA’s antibribery provisions. Thus, the bill would not be triggered by the recent ‘bribery, yet no bribery’ cases (Daimler, BAE, and Siemens) … In these cases, despite DOJ allegations that would seem to establish that the company violated the FCPA’s antibribery provisions, none of these companies were charged with violating the FCPA’s antibribery provisions. Instead, non-FCPA charges or FCPA books and records and internal controls violations were charged in an attempt to avoid application of the European Union debarment provisions. …


The big picture flaw with H.R. 5366 (as currently drafted) is it assumes all FCPA enforcement actions are resolved through judicial proceedings and it assumes all FCPA enforcement actions are resolved with charges that actually fit the facts.

Neither of these assumptions are accurate ….

So perhaps H.R. 5366 is not the giant-killer its drafters hoped it would be. The biggest targets will likely continue to skate around the FCPA rocks without tripping. But for other (smaller) companies, it might be the “death penalty” as they lose the ability to be awarded new U.S. Government contracts, based on a poorly crafted settlement agreement.

 

Pentagon Unveils Tactics to Drive Affordability in Defense Acquisitions

E-mail Print PDF

 


In May, 2010, Secretary of Defense Gates unveiled his initiative to drive down the cost of weapon systems and reduce Pentagon bureaucracy. Calling for long-term savings of nearly $102 billion, he said—

The goal is to cut our overhead costs and to transfer those savings to force structure and modernization within the programmed budget. In other words, to convert sufficient ‘tail’ to ‘tooth’ to provide the equivalent of the roughly two to three percent real growth – resources needed to sustain our combat power at a time of war and make investments to prepare for an uncertain future. Simply taking a few percent off the top of everything on a one-time basis will not do. These savings must stem from root-and-branch changes that can be sustained and added to over time.

Undersecretary of Defense (Acquisition, Technology & Logistics) Dr. Ashton Carter quickly responded to his leader’s call for action. On June 28, 2010, he met with defense industry leaders and called for savings of $66.3 billion over five years, to be found on current programs and activities. He said—

We need to restore affordability to our programs and activities … by identifying and eliminating unproductive or low-value-added overhead; in effect, doing more without more. … The guidance will focus on getting better outcomes, not on our bureaucratic structures.  … Most of the rest of the economy exhibits productivity growth, meaning that every year the buyer gets more for the same amount of money.  So it should be in the defense economy.

At that time, Dr. Carter issued a Memorandum addressed to Defense acquisition professionals. Entitled “Better Buying Power: Mandate for Restoring Affordability and Productivity in Defense Spending,” the Memo called for “delivering better value to the taxpayer and improving the way the [Defense] Department does business.”

We wrote about the new initiatives here.

Despite some initial confusion over terms, what have emerged are two distinct lines of attack: (1) the drive to reduce waste, bureaucracy, and inefficiency within the Pentagon, and (2) the drive to reduce the costs of goods and services by focusing on reducing contract prices. To clarify, we call them the “efficiency” and the “affordability” initiatives. We explored the two lines of attack in this article. The drive for Pentagon efficiency seems to be led by SecDef Gates, while the drive for contractor affordability seems to be led by USD (AT&L) Dr. Carter. In our latest article, we focused on SecDef Gates’ August 9, 2010, press conference and his “series of initiatives designed to reduce overhead, duplication, and excess in the Department of Defense, and, over time, instill a culture of savings and restraint in America’s defense institutions.”

Today’s article focuses on the other initiative, Dr. Carter’s quest to create billions of dollars of acquisition savings through driving down the prices paid by the Pentagon for weapon systems and services. On September 14, 2010, Dr. Carter unveiled the tactics he will employ in his attack on acquisition costs. We will discuss two documents: (1) a single-page “Guidance Roadmap” that provides plans on five specific areas of attack, and (2) a new “Better Buying Power” Memorandum for Acquisition Professionals.

Dr. Carter’s Guidance Roadmap listed five specific areas of attack in the drive to reduce Defense acquisition costs. These areas included:

  • Target Affordability and Control Cost Growth

  • Incentivize Productivity & Innovation in Industry

  • Promote Real Competition

  • Improve Tradecraft in Services Acquisition

  • Reduce Non-Productive Processes and Bureaucracy

The Guidance Roadmap document can be found via the link, above. Note it included specific sub-bullet points beneath each of the five lines of attack listed above.

The accompanying Memo, entitled “Better Buying Power: Guidance for Obtaining Greater Efficiency and Productivity in Defense Spending,” provided details on specific tactics Dr. Carter intends for his acquisition corps to deploy. There are 23 “principal actions to improve efficiency” linked to the five lines of attack listed above. Here is the 9/14/2010 Memo, and it is definitely worth reviewing in considerable detail.

We will not go through every word of the 17-page Memo, or review each of the 23 individual “principal actions”. What we want to do is to highlight some of the significant (and dare we say controversial?) tactics the Pentagon has been directed to utilize in the fight against acquisition costs. Here are some of the interesting aspects of Dr. Carter’s affordability initiative—

  • Reward contractors for successful supply chain and indirect expense management. This involves rewarding performance through setting appropriate profit levels. “Higher profit should be awarded to management of higher-risk subcontracts, and higher profit should be given when the prime succeeds in driving down subcontractor costs every year.” The Director of Defense Procurement and Acquisition Policy (DPAP) will “review the Weighted Guidelines … with the aim of emphasizing the tie between profit and performance.” Dr. Carter emphasized, however, that this was not simply an exercise in cost-cutting. He said—

    • It is important to note that the savings to be expected from this direction will be in cost, not in profit. Savings are not expected in profit per se since in some instances profit will increase to reward risk management and performance. But if profit policy incentivizes reduction in program cost, the overall price to the taxpayer (cost plus profit) will be less.

  • Reverse a decade of practice and restore DOD’s preference for using customary progress payments based on cost incurred, with other contract financing options being agreed-upon only with a commensurate reduction in contractor profit, based on increased cash flow.

  • Increase focus on contractor IR&D expenditures, “to improve the return on IRAD investments for industry and government.”

  • When only one bid or offer is received by the DOD, require Contracting Officers to obtain non-certified cost or pricing data, even if the FAR definition of “adequate competition” has been met.

  • The Director of DPAP will “develop guidance that will clearly spell out the roles and responsibilities” of DCMA and DCAA in order to avoid duplication and overlapping roles.

  • Use Forward Pricing Rate Recommendations (FPRRs) in lieu of Forward Pricing Rate Agreements (FPRAs). In particular, “where DCAA has completed an audit of a particular contractor’s rates, DCMA shall adopt the DCAA recommended rates as the Department’s position with regard to those rates.”

While some of Dr. Carter’s plans seem like good ideas, others disappoint us and strike us as counter-productive. For instance, we are disappointed to see the end of DOD’s regulatory preference for Performance-Based Payments and the return of customary progress payments. The debacle of the A-12 program taught many that progress payments had little to do with actually making progress, and everything to do with the ability to spend money. It looks to us like that lesson has been forgotten.

The substitution of DCAA audit findings for DCMA discretion and negotiation ability strikes us as a spectacularly bad idea, one that further shrinks the regulatory role of the Contracting Officer in favor of findings from an agency that has, in recent years, generated audit reports of poor quality that were, at the same time, dramatically untimely. We have reported many times on problems with recent DCAA audit guidance, and we see no indication that Dr. Carter’s direction will do anything other than cause financial problems for the defense industrial base.

As always, stay tuned for further developments.


 

The Wheels of Justice Continue to Roll and Contractors Feel the Pressure

E-mail Print PDF





It’s hard to keep from shaking the head and saying, “Tsk, tsk,” when we keep reading stories about contractors who fail at government contracting. Or as their attorneys might argue, “who find themselves in a difference of opinion with the Department of Justice regarding the propriety of certain contract-related billings.” Let’s remember that all contractors are innocent until proven guilty in a court of law—or until they reach a negotiated settlement with the DOJ.

Our first story today concerns the company, U.S. Foodservice. The company is based in Rosemont, Illinois, and was formerly owned by Royal Ahold NV, a giant supermarket conglomerate based in Europe. In 2007, the company was sold to private equity firms Clayton Dubilier & Rice Inc. and Kohlberg Kravis Roberts & Co. for $7.1 billion.

According to this story at Bloomberg Businessweek, U.S. Foodservice agreed to pay the U.S. Government $30 million in order to “settle a fraud lawsuit claiming it used shell companies to overcharge the Defense Department and the Department of Veterans Affairs for products at military bases.”

The article reported that U.S. Foodservice was awarded multiple contracts from 2000 through 2005 to supply military installations. The article reported these were “cost-based contracts,” but also reported that “under the contracts, U.S. Foodservice was only allowed to charge the price it paid for acquiring each product the government ordered, plus a pre-determined ‘add-on fee.’” Given that cost-plus-percentage-of-cost contracts are illegal, it’s not exactly clear what the contractual billing arrangement was supposed to be.

Apparently, something very like the requirements of FAR 31.205-26(e) were in place. Readers may remember our previous story about Bell Textron, who in May, 2010, agreed to pay the U.S. Government $16.6 million for overcharging the government from improperly billing its affiliated entities.

According to the Bloomberg story (which quoted the DoJ press release)—

U.S. Foodservice created shell companies, which were known within the company as ‘third-party billing entities’ and later called ‘value-added service providers,’ or ‘VASPs.’ … At U.S. Foodservice’s direction, the VASPs were told to ‘resell’ the same goods to the company and the government was billed for the higher amount shown on VASP invoices… The shell companies passed back to U.S. Foodservice the difference between the actual cost of the food products and the inflated amount they charged the government...

The Bloomberg article noted that—

More than a dozen people were charged in a related criminal case brought by the U.S. Attorney’s office in Manhattan. They included U.S. Foodservice’s former finance chief, Michael Resnick, who pleaded guilty to conspiracy and was sentenced to six months of house arrest.

According to this article at the Wall Street Journal—

U.S. Foodservice was previously at the center of a fraud case that alleged the company overstated the amount it was receiving in supplier rebates, known as promotional allowances. The company allegedly overstated those rebates by hundreds of millions of dollars to meet income targets.

That same article noted that—

In 2004, Ahold settled U.S. Securities & Exchange Commission charges that accounting issues led it to overstate net sales by about $30 billion from fiscal 2000 through fiscal 2002, including artificially inflating payments to U.S. Foodservice by vendors. Ahold cooperated with the SEC and wasn't fined.


In 2005, Ahold agreed to pay $1.1 billion to shareholders to settle a separate civil lawsuit in the U.S. over its accounting.


In 2007, Ahold agreed to sell U.S. Foodservice to a group of private-equity investors.

We should note that the company has its own view of the situation. The Bloomberg article reported that—

U.S. Foodservice said in an e-mailed statement that it fully cooperated in the probe. ‘We deny any wrongdoing and stand behind our pricing policies and practices, which have always been consistent with the terms of our federal government contracts and industry standards,’ the company said. ‘We settled because we want to close this chapter in our past.’

In somewhat related news, a couple of former Department of Energy contractors are in the process of learning about the wheels of justice, first-hand. This DOJ announcement reported—

a scientist and his wife, who both previously worked as contractors at the Los Alamos National Laboratory (LANL) in New Mexico, have been indicted on charges of communicating classified nuclear weapons data to a person they believed to be a Venezuelan government official and conspiring to participate in the development of an atomic weapon for Venezuela, among other violations.

The 22-count indictment … charges the defendants with conspiring to communicate and communicating ‘Restricted Data’ to an individual with the intent to injure the United States and secure an advantage to a foreign nation. They are also charged with conspiring to and attempting to participate in the development of an atomic weapon, as well as conspiring to convey and conveying classified ‘Restricted Data.’ The indictment further charges Mascheroni with concealing and retaining U.S. records with the intent to convert them to his own use and gain, as well as six counts of making false statements. Roxby Mascheroni is also charged with seven counts of making false statements.

Misbilling the U.S. Government is one thing. Corporations can settle with the U.S. Government; CFOs can receive six months of house arrest. But selling secrets can be an entirely different issue, as these two individuals are about to learn.




 

DOD Oversight Wars Continue: Inspector General Faces Criticism

E-mail Print PDF




DCAA is in the process of publishing new audit guidance that we can’t wait to share with you. But in the meantime, the Pentagon is facing renewed criticism, including allegations of oversight failures by the DOD Inspector General (IG). As readers may recall, the DOD IG has not hesitated to point a finger at the failings of the DCAA—so it seems apt justice that they start to feel some of the heat as well.



DOD Inspector General “Does Less with More”


On September 9, 2010, Robert Brodsky reported at GovExec.com that Senator Charles Grassley (R-Iowa) released a report that was highly critical of the DOD IG. Mr. Brodsky reported that Senator Grassley accused the DOD IG of failing to pursue any oversight reviews of any major weapon system or contractor in FY 2009, “leaving that mission to the DCAA.” As the GovExec article reported—


As the [Office of Inspector General] has drifted away from its core mission of conducting contract audits, it chose to move in an ill-advised direction,’ the 73-page report said. ‘Today, the majority of audits appear to be nothing more than quasi-academic reviews of DoD policies and procedures. The DoD OIG has become the department's 'policy police.' ‘ …



Overall, the 765-person audit office issued just 113 reports in fiscal 2009, its lowest total in two decades. In 1995, when the office had 717 auditors, the IG published 264 reports, the Senate staffers said. …



And despite conducting less labor-intensive contract audits, the office is averaging 18 months to issue reports, Grassley's staff found. Some audits have dragged on longer than three years, and others have taken so long the IG eventually scrapped them.


Not content with issuing the report, Senator Grassley also sent a letter to Secretary of Defense Gates, calling for “significant audit reforms” to the Office of the IG, according to Brodsky.


We spent some time looking at the Grassley report. There was plenty of criticism for all facets of DOD IG operations, ranging from an inability to audit DOD accounting data because of system limitations, to poor morale, to looming problems with financial statement audits of DOD components. But to us, the most interesting portion of the report was the portion devoted to “Acquisition and Contract Management (ACM).”


The Grassley report stated, “ACM has 162 auditors assigned to 26 branches spread across 9 divisions. There are an additional 11 persons assigned to the Front Office, including one SES executive, three senior auditors, one contract specialist, and 6 administrative personnel.” In Government Fiscal Year 2009, ACM’s auditors “produced a total of 28 reports.” According to Senator Grassley’s staff, that worked out to “an average of .173 audits per auditor per year.”


The Grassley report noted that, given the name and mission, one might think the ACM auditors focused on auditing contract payments. According to the report, one would be wrong to make that assumption.


ACM senior management repeatedly stated that ‘we don’t examine contract payments, and we don’t rely on DCAA to do it, either.’ They also said: ‘it’s impossible to audit contracts … We can’t do it …..It’s too hard to find transaction-level data, or it just doesn’t exist.’ They can’t do contracts, they said, because of ‘missing documentation and no audit trails.’ They indicated that ‘we used to do big weapons contracts but we lack the right skill sets – or experienced staff – to do it today.’ A top Audit Office official said they could ‘cobble together such an audit team to look at one of the big Category I weapons systems,’ but doing that would ‘deplete resources needed to meet other priorities.’


The Grassley report opined that, “De-coupling payments from contracts, as is the ACM practice, greatly reduces the probability of detecting and reporting fraud. In fact, it just about eliminates that possibility altogether.”


The Grassley report focused on one audit performed by the DOD IG ACM staff in FY 2009 as an example of what worked and didn’t work. The report (D-2009-108) was entitled “U.S. Air Forces Central War Reserve Material Contract” and it documented the audit of a cost-plus-award-fee contract awarded to DynCorp for managing pre-positioned war reserve materials (WRM) at storage sites in Southwest Asia. The Grassley report summarizes the DOD IG audit report as follows—


The most troublesome findings were buried deep in the body of the report. These are as follows:


  • The contract arrangement with DynCorp was prohibited by 10USC2306[a];

  • Once Operation Enduring Freedom caused a major surge in WRM requirements far beyond the scope of the existing contract, that contract should have been terminated in FY 2002-03 and re-competed;

  • Missing documentation resulted in either no audit trail or one so complex that accountability was questionable; The lack of internal controls created an environment with “high risk” for fraud;

  • DynCorp was authorized to submit vouchers directly to DFAS under the Direct Billing program; DCAA was required to test and sample those transactions periodically but failed to do so;

  • $161.1 million was obligated without a written, binding agreement in violation of 31USC1501…


The Grassley report continued—


The [DOD IG audit] report appears to imply that the vouchers, for the most part, could not be matched with the contract modification documents because the language in those documents did not specify what goods and services had to be delivered. If a payment/contract match-up was not feasible, this could be a violation of 31 USC § 1501. That law requires that a financial obligation be supported by a written, binding agreement (contractual document) that specifies what goods and services are to be delivered. Without that kind of specificity, a contract would be the equivalent of a blank check. The report stated: the government did not know what it was paying for … The government may have paid for services DynCorp did not perform. … It may have overpaid for services.” In other words, the government did not know what it had ordered, what was delivered, or what it was actually buying or paying for.


To conclude, Grassley’s staffers offered the following summary—


All of this taken together appears to suggest that DynCorp may have received $161.1 million in unauthorized and/or improper or even fraudulent payments. But the report’s findings are inconclusive.


The OIG recommended that DCAA go back and examine this DynCorp contract. However, bucking this audit back to DCAA made no sense whatsoever. To begin with, the report gave DCAA very poor grades for failing to watchdog DynCorp on this contract from the get-go. The DOD IG should finish the audit that it started.


Whew. That sounds bad.


What did the DOD Inspector General say in response to such criticism?


On September 13, 2010, DOD Inspector General Gordon S. Heddell issued a response to Senator Grassley’s criticisms. In his letter to Senator Grassley, Mr. Heddell stated—


I believe that your report presents valid concerns and is an opportunity to enhance the mission of the Department of Defense Inspector General (DoD IG) in regard to detecting and reporting fraud. Therefore, I have directed the Deputy Inspector General for Auditing and her staff to make concrete and specific proposals on how your report can be used to improve the timeliness, focus, and relevance of audit reports. Furthermore, I have directed that these proposals, to be completed no later than October 15, 2010, are supplemented by a detailed plan listing specific initiatives to be implemented at the earliest possible date. The recommendations in your report will be an important tool in the transformation I have initiated since being confirmed as Inspector General.


The letter included more detailed responses to each of the 12 criticisms found in the Grassley report. And by “more detailed responses” we mean such detailed responses as the following—


As noted in the response to recommendation 2, "end-to-end" contract performance and payout audits involve an extensive amount of resources and time to complete and which, by the very nature of their wide scope, could exacerbate the very issues the report highlights involving timeliness. Instead, we provide audit coverage of the contract process through a series of audits based on the risks associated with the specific contract segment.


To further strengthen this approach, the DoD IG focus on finance and accounting systems has been expanded to include oversight of plans and programs to acquire new accounting systems and efforts to modernize the existing systems.


Well, that response really ought to placate Senator Grassley and his staffers, who think the DOD IG is failing at its oversight mission. Right?






 


Page 222 of 277

Newsflash

Effective January 1, 2019, Nick Sanders has been named as Editor of two reference books published by LexisNexis. The first book is Matthew Bender’s Accounting for Government Contracts: The Federal Acquisition Regulation. The second book is Matthew Bender’s Accounting for Government Contracts: The Cost Accounting Standards. Nick replaces Darrell Oyer, who has edited those books for many years.